The school was opened last year in a extremely poor area of India. There are 80 students in two classes. Volunteers of AMURT visit that area every year to hold medical camps and distribute blankets and clothes in winter. Presently the school is running in a house. The school building is under construction. The most urgent work is the roof. Below is the budget to complete the school building:

- Present uncompleted School Building (20' x 50')

BUDGET FOR ROOF CONSTRUCTION - Amounts in Rupees - US$1 = approximately Rps.38

Tata metal roof sheet- 50,000
Iron pipe- 20,000 ( 50 rupees/feet
nuts and bolts 1300
Washers 300
Cement 6900 ( 230 rupees/packet----30 packet we need
Sand 2000 ( 4 trucks), 500 rs / trucks
Brick 2000 ( 1 truck),some bricks already available
Head worker 7500 ( 150 /day ) for 15 days
Labor 1500 ( 100/day ) for 15 days
----------------------------
Total 91,500/- - Approximately US$2,500

Prepared by:
Dinesh Kumar and Ramlakhan Singh
UBP, Satbarwa
Palamau, Jharkhand